Lien Waivers in Florida: Conditional vs. Unconditional, and What You Are Really Signing
Lien waivers change hands on almost every Florida construction payment. Signing the wrong one, or signing before you are paid, can cost you your lien rights. Here is how they work.
A lien waiver is a document in which a contractor, subcontractor, or supplier gives up some or all of its right to record a construction lien against the property, usually in exchange for payment. Owners and lenders want them before releasing money. Contractors and subs sign them to get paid. They are routine, and that is exactly why people sign them without reading closely.
Why lien waivers matter
Florida's Construction Lien Law, Chapter 713, lets people who improve real property record a lien if they are not paid. That right is one of the strongest tools a contractor or supplier has. A lien waiver gives part of it up. Signed at the wrong time or for the wrong amount, it can leave you with no lien rights for money you never received.
For owners, collecting proper waivers is one of the main ways to avoid paying twice, once to the general contractor and again to a sub or supplier who was not paid down the line.
Florida's statutory forms
Section 713.20 of the Florida Statutes provides two forms:
- Waiver and release of lien upon progress payment, which releases lien rights for work through a specific date, in exchange for a specific payment.
- Waiver and release of lien upon final payment, which releases all lien rights for the job once final payment is made.
Florida law says a person may not require a lienor to furnish a waiver that is different in substance from the statutory forms. Florida also prohibits waiving lien rights in advance. A clause in a contract that says the sub gives up its lien rights before doing the work is generally unenforceable.
Conditional versus unconditional
Outside Florida, many states have separate statutory forms for conditional and unconditional waivers. Florida does not use those labels in its statute, but the concept matters:
- An unconditional waiver is effective when signed, whether or not the payment actually clears.
- A conditional waiver only becomes effective once the stated payment is actually received.
Because Florida's forms state that the waiver is given upon receipt of the stated payment, how and when you deliver a signed waiver matters. Contractors who hand over a signed waiver before a check clears take the risk that the payment never arrives. Many contractors deliver waivers only at the same time as payment, or only after funds clear, and some parties add language tying the waiver to receipt of good funds. Talk with counsel before modifying the statutory form, given the rule against requiring waivers different in substance.
Common mistakes
- Signing a final waiver when you have only received a progress payment.
- Signing a waiver for an amount larger than what you were actually paid.
- Signing a waiver "through" a date that includes work you have not been paid for, including unapproved change orders.
- Not tracking which waivers you have signed on which job.
- For owners, paying the general contractor without collecting waivers from subs and suppliers who served a notice to owner.
For owners: waivers and the final payment affidavit
Before a contractor can enforce a lien, it generally must provide the owner a contractor's final payment affidavit listing any lienors who have not been paid. Collecting waivers throughout the job, and checking them against the notices to owner you receive, is the best way to avoid surprises at the end.
If you are dealing with a waiver dispute, or you signed a waiver and were not paid, our construction lien attorneys can review your options. Contact us to schedule a consultation.
Sources
Frequently Asked Questions
Can a Florida contractor waive lien rights in advance?
No. Florida law prohibits waiving lien rights in advance of furnishing labor, services, or materials. Waivers are given in exchange for payment.
What is the difference between a conditional and unconditional lien waiver?
An unconditional waiver is effective once signed. A conditional waiver only takes effect when the stated payment is actually received. Florida's statutory forms are tied to receipt of payment, but timing of delivery still matters.
Do I have to use Florida's statutory lien waiver form?
Florida provides statutory forms, and a lienor cannot be required to furnish a waiver that is different in substance from them.