Latent Construction Defects in Florida: Chapter 558 Notices and Your Options
Some construction defects do not show up for years. Here is how Florida treats hidden defects, the required pre-suit notice process, and what owners should do first.
A construction defect is a flaw in design, materials, or workmanship that makes a building fail to perform as it should. Some defects are obvious right away. Others hide behind stucco, under a roof, or inside a wall until water damage or cracking appears years later. Florida law treats those two kinds differently, and the deadlines are strict.
Latent versus patent defects
- A patent defect is one a reasonable inspection would reveal, such as visibly uneven floors or a missing handrail.
- A latent defect is hidden and would not be discovered by a reasonably careful inspection, such as improper flashing behind stucco, missing rebar, or inadequate waterproofing.
The distinction matters because it affects when the clock starts on a claim. Florida law sets filing deadlines for construction defect claims, including an outside limit that can bar a claim even when the defect was just discovered. Those deadlines are strict, so have them reviewed as soon as you find a problem.
The Chapter 558 pre-suit process
Before filing a construction defect lawsuit against a contractor, subcontractor, supplier, or design professional, Florida law generally requires the owner to serve a written notice of claim under Chapter 558. In broad terms:
- The owner serves a written notice describing the defects in reasonable detail before filing suit.
- The recipient may inspect the property.
- The recipient responds, and may offer to repair, offer to pay, dispute the claim, or a combination.
- The owner can accept or reject the offer, and if rejected or not resolved, may proceed to suit.
The Chapter 558 rules are technical. Contracts sometimes allow the parties to opt out of Chapter 558 if the contract says so in the required way.
What owners should do when they find a defect
- Document it with dated photos and notes. Keep any water damage from getting worse with reasonable temporary measures, and keep receipts.
- Gather the contract, plans, permits, warranties, inspection reports, and correspondence.
- Notify your insurer if there is resulting damage.
- Avoid tearing out the defective work before it can be inspected. Evidence matters.
- Get legal advice before you negotiate informally.
Who can be responsible
Depending on the defect, potentially responsible parties include the general contractor, subcontractors, suppliers and manufacturers, architects and engineers, and in some cases developers or sellers. Florida's building code also provides a statutory cause of action for certain knowing code violations, which has its own requirements.
Our construction defect attorneys represent owners and businesses in Chapter 558 notices, negotiations, and litigation. Contact us to schedule a consultation.
Frequently Asked Questions
What is the difference between a latent and a patent defect?
A patent defect is one a reasonable inspection would reveal. A latent defect is hidden and would not be found by a reasonably careful inspection, such as improper flashing behind stucco.
Should I fix a construction defect before talking to a lawyer?
Take reasonable steps to prevent further damage, like temporary water protection, but avoid tearing out defective work before it can be inspected and documented.
What is a Chapter 558 notice?
A written pre-suit notice that Florida generally requires owners to serve on contractors, subcontractors, suppliers, or design professionals before filing a construction defect lawsuit, giving them a chance to inspect and respond.